JAA will receive bids electronically, until 2:00 PM (local time) on June 16, 2026, via DemandStar. HAND DELIVERED, MAILED, FAXED OR EMAILED BIDS WILL NOT BE ACCEPTED.
To register with DemandStar, visit: https://www.demandstar.com/registration
The overall scope of this project involves the selective demolition of a portion of the existing hourly parking garage at Jacksonville International Airport. Work includes the barricading and restriction of designated areas of the garage at Levels 2, 3, and 4 to facilitate demolition of the fire-damaged sections, as documented. The life safety analysis confirms that adequate means of egress and paths of travel are maintained throughout the demolition activities, despite the temporary closure of the two southernmost stairwells and the affected portion of the garage.